In progressJob J-204
Master Bath Gut Remodel
Elena Park · 1418 Linden Ave, Oakland CA
Financial summary
Budget
$28,400
Spent
$18,620
Remaining
$9,780
Est. margin
40%
Cost burn66%
Cost breakdown
$17,148| Item | Cat | Qty | Unit | Total |
|---|---|---|---|---|
| Demolition & disposal | labor | 1 | $1,850 | $1,850 |
| Plumbing rough-in | subcontract | 1 | $3,400 | $3,400 |
| Porcelain tile (large format) | materials | 220 | $10 | $2,090 |
| Walk-in shower glass | materials | 1 | $2,200 | $2,200 |
| Floating walnut vanity | materials | 1 | $3,100 | $3,100 |
| Carpenter labor (Marcus, Tasha) | labor | 86 | $48 | $4,128 |
| City permit | permit | 1 | $380 | $380 |
Photo log
3 photos
Demo complete — old tile + plumbing pulled.
Marcus R.Apr 3 · 9:14 AM

Rough-in inspection passed. Drywall going up Friday.
Tasha C.Apr 14 · 4:02 PM

Tile complete. Glass + vanity install Monday.
Marcus R.Apr 18 · 11:40 AM