In progressJob J-204

Master Bath Gut Remodel

Elena Park · 1418 Linden Ave, Oakland CA

Financial summary

Budget
$28,400
Spent
$18,620
Remaining
$9,780
Est. margin
40%
Cost burn66%

Cost breakdown

$17,148
ItemCatQtyUnitTotal
Demolition & disposallabor1$1,850$1,850
Plumbing rough-insubcontract1$3,400$3,400
Porcelain tile (large format)materials220$10$2,090
Walk-in shower glassmaterials1$2,200$2,200
Floating walnut vanitymaterials1$3,100$3,100
Carpenter labor (Marcus, Tasha)labor86$48$4,128
City permitpermit1$380$380

Photo log

3 photos
Demo complete — old tile + plumbing pulled.
Demo complete — old tile + plumbing pulled.
Marcus R.Apr 3 · 9:14 AM
Rough-in inspection passed. Drywall going up Friday.
Rough-in inspection passed. Drywall going up Friday.
Tasha C.Apr 14 · 4:02 PM
Tile complete. Glass + vanity install Monday.
Tile complete. Glass + vanity install Monday.
Marcus R.Apr 18 · 11:40 AM