BuildPro
Elena Park
Project J-204
Your project

Master Bath Gut Remodel

Started
Apr 2
Estimated finish
May 8
Status
On schedule

Budget tracker

Updated live
Spent so far
$18,620
Total budget
$28,400
Remaining
$9,780
66% of budget used7 itemized costs
!

Needs your approval

Heated tile floor upgrade
Add electric radiant heat mat under shower & main floor (~42 sqft). Includes thermostat.
+$1,280

Invoices

INV-204-A
Due Apr 5
$9,000
Paid
$
INV-204-B
Due Apr 22
$8,200

Itemized costs

Demolition & disposal
labor
$1,850
Plumbing rough-in
subcontract
$3,400
Porcelain tile (large format)
materials · 220 × $10
$2,090
Walk-in shower glass
materials
$2,200
Floating walnut vanity
materials
$3,100
Carpenter labor (Marcus, Tasha)
labor · 86 × $48
$4,128
City permit
permit
$380
Replace rotted subfloor section Approved CO
Discovered 6 sqft of water-damaged subfloor under old vanity. Replace + seal.
+$420

Latest from the crew

Demo complete — old tile + plumbing pulled.
Demo complete — old tile + plumbing pulled.
Marcus R.Apr 3 · 9:14 AM
Rough-in inspection passed. Drywall going up Friday.
Rough-in inspection passed. Drywall going up Friday.
Tasha C.Apr 14 · 4:02 PM
Tile complete. Glass + vanity install Monday.
Tile complete. Glass + vanity install Monday.
Marcus R.Apr 18 · 11:40 AM

Project timeline

Every photo, update, approval, and payment — in one place.

  1. 💬
    UpdateApr 3
    Demo done, dumpster picked up. Site is clean.
    by Marcus R.
  2. 💬
    UpdateApr 11
    Rough plumbing inspection passed first try ✅
    by Tasha C.
  3. 💬
    UpdateApr 18
    Wall tile complete. Looks even better than the sample.
    by Marcus R.
  4. 📷
    PhotoApr 18 · 11:40 AM
    Progress photo uploaded
    Tile complete. Glass + vanity install Monday.
    by Marcus R.
  5. 📷
    PhotoApr 14 · 4:02 PM
    Progress photo uploaded
    Rough-in inspection passed. Drywall going up Friday.
    by Tasha C.
  6. 📷
    PhotoApr 3 · 9:14 AM
    Before photo uploaded
    Demo complete — old tile + plumbing pulled.
    by Marcus R.
  7. Approved$420Apr 9
    Customer approved: Replace rotted subfloor section
    by Elena Park
  8. 📋
    Change order$420Apr 9
    Change order proposed: Replace rotted subfloor section
    Discovered 6 sqft of water-damaged subfloor under old vanity. Replace + seal.
    by Office
  9. 📋
    Change order$1,280Apr 18
    Change order proposed: Heated tile floor upgrade
    Add electric radiant heat mat under shower & main floor (~42 sqft). Includes thermostat.
    by Office
  10. $
    Invoice$8,200Apr 22
    Invoice INV-204-B sent
    Due Apr 22
    by Office
  11. Paid$9,000Apr 5
    Payment received · INV-204-A
    by Elena Park
  12. $
    Invoice$9,000Apr 5
    Invoice INV-204-A sent
    Due Apr 5
    by Office

Your crew lead

Marcus Reyes
Marcus Reyes
Lead Carpenter